9/6/14- Placed a hold on lot 41
9/7/14- Signed a purchase agreement for Courtland Gate, switched lots from 41 to 14
9/11/14- Met with NVR loan officer, signed loan paperwork (keeps fingers crossed)
9/14/14- Signed addendum for structural changes (added windows and garage service door)
9/18/14- Picked out flooring, back splash, and tile for bathrooms
Had phone interview with actual bank that would be providing the loan;
pre approval given on the spot. Waiting for underwriting to complete their end.
9/25/14- Met with Guardian, to set up wireless network, a couple of pre wires and
an alarm system
9/27/14 - Final selections made, the wait game begins
11/4/2014- Request for Updated Information from Amerihome (grrr!)
11/5/2014- Schedule Pre construction meeting
11/13/14- Loan paperwork finally submitted to underwriting. They have 72 hours to respond
11/20/14- Pre construction meeting, scheduled to break ground the week of 11/24. Loan in que-
underwriters had 40 loans to process since last week.
11/24/14 Broke Ground!
11/29/14- Footers in place
12/3/14- Forms in place
12/5/14 - Foundation in place
12/09/14- Conditional Loan Approval
12/16/14- Lumber has arrived
12/19/14- Basement Framed
12/21/14- First floor framed
12/28/14- Framed and Wrapped
12/31/14- HVAC, plumbing to start on Monday. Scheduled pre drywall inspection for 1/12, will do walk thru on 1/08/15!
1/08/15 Pre Dry Wall meeting- inspector scheduled to be on site 1/12/15
1/12/15 Pre Dry Wall inspection complete, few minor issues to resolve
1/17/15 Dry walled! Siding placement has begun
1/21/15- Delivery of some trim work
1/23/15- Received a call from PM that dry was complete and that inside trim work will begin
2/1/15- Kitchen cabinets and bathroom cabinets installed, balusters installed, chandeliers installed
wainscoting installed, dining room columns installed, master bath floor tiled, hall bath floor
tiled. some paint completed needs touch up
2/6/15- Kitchen cabinets completely installed with hardware, granite counter tops installed, hardwood
floors installed, crown molding in place. fireplace surround and mantle in place, WE HAVE
LIGHTS, master bathroom completely tiled, thermostat and security alarm panels installed
2/13/15- carpet installed, replaced kitchen cabinets, stairs and railings are being stained, lot has been
graded and topsoil added, walkways have been added
2/15/15- Staining of banisters and steps has begun, still waiting on railings for portico
2/25/15- exterior door painted, foyer window trimmed as well as decorative "vent" for garage and
attic
2/27/15- official lock and key hardware installed. Settlement company now has keys
Translation: LOCKED OUT; pre settlement scheduled for 3/06/15; closing scheduled
for 3/12/15
3/05/15- pre settlement rescheduled to 3/10/15
3/06/15- Huge discrepancies noted in our paperwork- submitted and resubmitted verification of
income.
3/10/15- pre settlement walk through complete; informed asset verification needed
3/11/15- post build inspection complete
3/16/15- loan paperwork finally resubmitted to underwriters
3/25/15- received GFE and locked rate
4/1/15- CLOSED
No comments:
Post a Comment